Amendment No. 01 Responses to RFIs received by 1/16/2024. Question: Could you please clarify if the A/E will be required to submit updated statistical schedule risk analysis throughout the constructio...
Amendment No. 01 Responses to RFIs received by 1/16/2024. Question: Could you please clarify if the A/E will be required to submit updated statistical schedule risk analysis throughout the construction phase or is just only for the design phase? On attachment 3 uploaded in SAM and under SPEC 01 32 16.01 Section 1.13 A. Project Design Schedule Risk Analysis/Mitigation Plan, states: the "A/E shall conduct the statistical schedule risk analysis based on the above detailed construction activities." Response: It would only be submitted during the design phase based off their anticipated construction CPM for the project