The purpose of this amendment is as follows: Question - Is this the design portion ONLY or will the designer also be installing the proposed design? Answer - This is not a design build action, it s fo...
The purpose of this amendment is as follows: Question - Is this the design portion ONLY or will the designer also be installing the proposed design? Answer - This is not a design build action, it s for the design only and the offeror who designs may not propose on the construction. Question - If the solicitation is for the design only then will the company that designs the project be able to bid the construction portion? Answer Refer to answer No 1. ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED.