Z1DA--556-24-113 Oil Transformer and Switch Enclosure Upgrades
This project involves replacing medium voltage oil-filled transformers and electrical switchboards at the Captain James A. Lovell FHCC in North Chicago, IL. The contractor must provide all labor, materials, and supervision for renovations across multiple campus buildings, including relocating one transformer and installing new concrete pads and anti-ram bollards. The total period of performance is 357 calendar days from the Notice to Proceed, with key milestones including a 14-day submission period and a 215-day timeline for the longest lead item delivery. The contractor is responsible for expediting planning to avoid interruptions, particularly around long lead equipment procurement. A single pre-bid conference will be held for prospective bidders to observe site conditions, but no questions will be permitted during that event.