Y1DA--Surgical HVAC Systems Replacement 556-23-127
This project involves the complete renovation and replacement of two air handling units (AHU-12 and AHU-1) serving surgical suites and administrative areas at the Captain James A. Lovell FHCC in North Chicago, IL. The period of performance is 388 calendar days from the Notice to Proceed to contract closeout. The work requires the contractor to provide all tools, materials, labor, and supervision to remove and replace all AHU components as specified. A mandatory pre-bid conference will be held for site observation, but all questions must follow a formal RFI process. Specific material requirements are detailed, such as prohibiting cast iron fittings and mandating the use of forged steel and ASTM A193 fasteners.