P400--Building 149 and 150 Demolition 552-26-201
This project involves the demolition of Buildings 149 and 150, where all materials must be treated as hazardous due to extensive structural failure, and the contractor is responsible for identifying and accounting for these materials for disposal. For utilities, steam and condensate piping must be removed back to a specified valve in Building 149, while in Building 150, the existing piping must be removed as its valve has already been capped. The work requires closing the corridor between Buildings 305 and 409 to foot traffic, and sections of an adjacent parking lot can be used for equipment staging, though a loading dock must remain accessible. The contractor is responsible for site restoration, including landscaping affected areas. No hazardous materials survey or testing was completed due to safety concerns.