Z1DA--Upgrade Campus Electrical Systems. Project No. 610A4-23-101.
This project involves a major electrical service upgrade for a campus, including the demolition of Building 16 and its existing electrical equipment and generators. The work includes constructing a 6,600 square foot addition to the south side of Building 1 to house new primary switchgear and installing three new 600 kW standby generators with associated automatic transfer switches and three new unit substations. The Government expects to publish responses to current Requests for Information around February 9, 2026. The performance location is the campus. No budget information is provided.