Correct Electrical Deficiencies
The project will correct electrical deficiencies at the Fayetteville VAMC, including a new electrical entrance building, medium-voltage loop replacement, distribution equipment replacements, grounding corrections, incidental electrical cleanup, and minor HVAC and plumbing improvements. Work will be phased, require a VA-approved phasing plan, and use temporary power to minimize outages in occupied areas. The period of performance is 1,174 calendar days. Alternate No. 1 would delete specified ground-conductor work in Building 1, Floors 1 and 3.