J041--558-22-172, Replace Chillers in AHU 1 and 2
The project involves replacing chillers for AHU 1 and 2, including associated equipment and structural upgrades, at a Department of Veterans Affairs medical center. Work must be phased to avoid disrupting the facility’s 24/7 operations, with utility outages requiring 20 days’ written notice and scheduling on second shift or weekends. The contractor must hold weekly progress meetings, submit meeting minutes and red-line as-built drawings, and comply with strict safety, hot work, and egress requirements while the building remains occupied. The contractor has 270 days from notice to proceed to complete the project.