J041--558-22-172, Replace Chillers in AHU 1 and 2
The project involves replacing chillers serving AHU 1 and 2, including associated equipment and structural upgrades, with all labor, materials, permits, and testing provided. Work must be phased to avoid interrupting the medical center's 24/7 operations, with utility outages requiring 20 days' written notice and approval, and hot work requiring permits 48 hours in advance. The contractor must hold weekly progress meetings, provide as-built drawings, and comply with strict safety, egress, and dust-protection requirements. All construction must be completed within 270 days of notice to proceed. The facility operates around the clock, so construction will occur across multiple shifts with minimal disruption to occupied areas.