J041--558-22-172, Replace Chillers in AHU 1 and 2
The contractor must replace chillers serving AHU 1 and 2, including associated equipment and structural upgrades, and provide all labor, materials, tools, equipment, permits, testing, and reports. The contractor will facilitate a pre-construction meeting, hold weekly progress meetings with COR/CO participation, provide minutes within 7 days, and submit red-line as-built drawings to the A/E. Work will occur in an occupied, 24/7 VA medical center and must be phased across shifts to minimize disruption; utility outages must be scheduled for second shift or weekends with a written shutdown request at least 20 days in advance. Site requirements include COR approval for storage, badges/ID for workers, egress and property protection, and hot-work permits obtained at least 48 hours in advance. The project must be completed no later than 270 days after issuance of the notice to proceed.