Z1NB--Boiler Replacement Sources Sought
This is a market survey for replacing three firetube boilers and related infrastructure at the Durham VA Medical Center. The anticipated budget for the construction is between $10 million and $20 million, with a performance period of 574 days from the Notice to Proceed. Work must be performed on-site in Durham, with specific construction and utility work required during designated first and second shifts. The government anticipates setting the acquisition aside for Service-Disabled or Veteran-Owned Small Businesses if possible. Interested vendors must email a detailed capabilities statement and responses to specific project questions by the provided deadline.