Y1DA--630A4-26-401 MRI AHU Modification
This is a design-build project for a dedicated cooling system for an MRI suite at the VA Medical Center in Brooklyn, NY. The performance period is 270 calendar days, with a construction magnitude between $500,000 and $1,000,000. The work involves installing a new air-cooled chiller, chilled water piping, and hallway fan coil units to provide year-round cooling for the MRI equipment. The contractor must integrate the new system with the existing Honeywell Building Automation System and complete all design, construction, and functional performance testing. The project requires a site visit, adherence to VA standards, and use of the Autodesk Build platform for project management.
Links (0)
Attachments (16)
Data sourced from SAM.gov.
View Official Posting »