Demolition, Removal, and Remediation
The contractor must prepare and submit a draft Work Plan within 10 business days after a kickoff meeting with Volpe Center representatives, detailing the technical approach for demolition, debris removal, disposal, and site restoration. The plan must incorporate a site survey review, waste characterization sampling, disposal facility identification, required permits, a Site Safety and Health Plan, and a Risk Management Plan. After submission, the contractor should allow a 5 business day Volpe Center review period before receiving comments, then must submit the Final Work Plan within 5 business days of receiving those comments. No specific performance location is stated beyond the Volpe Center's involvement, and no budget amounts are provided.