56--BPA Set-up for Raw Materials (Gravel) at OZAR
This amendment to a BPA setup for base rock, clean rock, and riprap provides Q&A clarifying that the required 20-mile distance is measured by driving distance via Google Maps or similar, and compliant material may be sourced outside that radius if stockpiled or loaded within the 20-mile area. The stockpile or loading location need not be owned or operated by the quarry, as long as it is within the 20-mile area and accessible by dump trucks. A compliant location must provide certified scales and weight tickets, suitable loading equipment, MoDOT-compliant materials, and availability within 72 hours of each BPA call. Performance is anticipated to begin on contract award, which is expected before the end of the current month. No additional permits or certifications are known to be required, but the government must be able to weigh compliant material on its trucks.