ON-SITE ELECTROCHLORINATOR SYSTEM REPLACEMENT SEATTLE, WA AMENDMENT I The purpose of this Amendment is to 1) answer submitted questions, and 2) extend the Quotes Due Date. No further questions will be...
ON-SITE ELECTROCHLORINATOR SYSTEM REPLACEMENT SEATTLE, WA AMENDMENT I The purpose of this Amendment is to 1) answer submitted questions, and 2) extend the Quotes Due Date. No further questions will be accepted. 1) QUESTIONS AND ANSWERS Q: What is the required dose rate of chlorine in the water? A: 2 PPM Q: What is the capacity of the existing electrochlorinator? A: 20 GPD Q: Please share the P&ID and component details of the existing unit, especially for the items that are not going to be replaced, like blower, brine tank, softener etc. so that we can review it. A: No information Q: Please provide the control philosophy of the existing unit. A: No information 2) QUOTES DUE DATE The due date for quote is extended FROM: 07/05/2022 at 0600 PDT TO: 07/08/2022 at 0600 PDT.