J--HAULOUT OF THE R/V STURGEON
The amendment addresses a question about Work Item 6.3, the ABS Survey for load line. Under the agreed change, the contractor will perform tasks supporting the vessel’s load line special survey to the ABS Surveyor’s satisfaction. The contractor remains responsible for scheduling and coordinating inspections with the ABS Surveyor. Any additional work the ABS Surveyor determines is necessary for the load line survey will be proposed by the contractor via a CFR. The Government agrees to this revised approach.