43--A3 WELL BOOSTER
The USGS Columbia Environmental Research Center requires the removal of an existing centrifugal pump and installation of two redundant inverter-duty pumps with a properly sized Variable Frequency Drive (VFD) and support controls, including BACnet-capable flow meters and pressure gauges. The work must be performed in Boone County, Missouri, with a 30-day performance period after the notice to proceed. The new pumps must handle 120 to 200 feet of head and flow 200 gallons per minute, with all circuits installed to current electrical codes. This acquisition is a 100% Small Business Set-Aside under NAICS code 333914, with a size standard of 750 employees. A site visit is scheduled for May 21, 2025, and attendance is strongly encouraged.