USCG Cutter Eagle New Dredging for Berthing at New London City Pier
The Government seeks a small-business contractor to perform new dredging immediately south of CGC Eagle’s berth at New London’s City Pier, CT, deepening to -17.0’ MLLW with a +2.0’ overdredge allowance and removing about 3,700 CY of dredge spoils to an upland disposal site; offshore disposal is not permitted. The scope also includes removal of approximately 50 submerged piles, cutting any unremovable piles at -21.0’ MLLW, and maintaining navigation through the channel at all times. Dredging is restricted to October 1 through March 1, and the performance period is estimated at 300 calendar days from Notice to Proceed. The estimated procurement value is between $1,000,000 and $5,000,000; a 20% bid guarantee and performance/payment bonds are required. This acquisition is FAR Part 14 sealed bidding and 100% set-aside for Small Business, with per-cubic-yard pricing to adjust for actual dredge quantities within the limits of dredge.