USCGC Alex Haley MRG Coolers Repair
This requirement is for the inspection, testing, and repair of two specific reduction gear coolers for the USCGC Alex Haley, with the base scope including the replacement of up to six tubes per cooler. The period of performance is from March 9 to April 17, 2026. The contractor will perform all work at their own designated repair facility. The government will furnish the two coolers, and the contractor is responsible for delivering the repaired items to 26 Albatross Ave, Kodiak, AK 99619. The contractor must comply with numerous technical manuals and procedures, provide detailed condition reports, and any repairs beyond the base scope require a separate written modification from the Contracting Officer.