Amendment 02 to provide an answer to a contractor question and extend the quote due date. The purpose of this Amendment 0002 is to 1) Provide response to a question submitted by the contractor, and 2)...
Amendment 02 to provide an answer to a contractor question and extend the quote due date. The purpose of this Amendment 0002 is to 1) Provide response to a question submitted by the contractor, and 2) change RFQ response date as follows: 1) Provided responses to proposed question: Question: Concerning Wall Mount Units, can buildings be modified to fit new equipment footprint? Government Answer: We can allow for the buildings to be modified for the new footprint for Wall Mount Units as per manufacture’s recommendations and applicable standards. 2) Change RFQ submission date as follows: From: 25 August 2021 To: 27 August 2021 Period of Performance: 08/26/2021 to 02/25/2022