Rosebud Lift Station Construction
This opportunity involves the full removal and replacement of an existing lift station at 1319 Soldier Creek Road, Rosebud, SD, to accommodate hospital and tribal program expansion. The project includes a new wet well, dry well, chopper pumps, force main connection, and a control system, with a performance period of 240 calendar days. The construction magnitude is between $500,000 and $1,000,000, under a firm-fixed-price contract, and is a total small business set-aside. TERO requirements apply, and brand names establish a standard of quality, with equal products allowed if they meet specified performance requirements. The existing lift station will be demolished after the new one is operational, sized for future growth.