Scope of Work: Source 4MW of temporary power system to include two 2MW diesel generators, 480V/12.47kV step up transformer(s) (if needed), manual closed transition transfer switch, and fuel tank. Prov...
Scope of Work: Source 4MW of temporary power system to include two 2MW diesel generators, 480V/12.47kV step up transformer(s) (if needed), manual closed transition transfer switch, and fuel tank. Provide equipment for rental between May 2021 to December 2021. Include load bank and transformer (if needed) during the testing/commissioning phase. Mobilize equipment at designated location and provide 24/7 operations when needed. This is to include knowledgeable personnel to run the equipment and fuel deliveries when needed. Operations are required for testing, during Public Safety Power Shutoff (PSPS) events, and any unforeseen outages. Excluded: Design of temporary power system, Pacific Gas & Electric Interconnection Permitting, and Installation.