Argon Piping Supply, Installation and Testing
The Department of Energy (DOE) is seeking a contractor to supply, install, and test a stainless-steel pipeline for transporting argon gas underground at the Long-Baseline Neutrino Facility (LBNF). The work involves piping of varying diameters (8-inch and 6-inch Schedule 10) from the Ross Shaft Argon Receiving station to the Central Utility Cavern (CUC) at the 4850 Level. The project supports the DUNE experiment, requiring the transport of approximately 40,000 metric tons of argon. Performance of services will be at the LBNF site, specifically involving the Ross Shaft and underground levels. No budget amounts or submission timelines are specified in the description.