Installation of Dedicated 120VAC and 240VAC Receptacles for Data Center Re-cabling Project
The Western Area Power Administration requires a contractor to install dedicated 120VAC and 240VAC receptacles for a data center re-cabling project in Phoenix, AZ 85009. The work includes furnishing and installing a code-compliant underfloor gutter system to distribute branch circuits to SCADA equipment racks and workstations. Feedback on the draft Statement of Work is encouraged, particularly regarding additional business documents, requirement clarifications, and experience in secure CIP-controlled areas. Responses must be submitted by email by June 17, 2026, at 2:00 PM Mountain Time, limited to three pages including company details and business size. No budget information is specified in the description.