REPAIR TAXIWAY A, Phase 1 and Phase 2 (Option) both Unfunded
This opportunity is for the Repair of Taxiway A at Vance Air Force Base in Enid, Oklahoma, with work including concrete pavement removal, joint seal replacement, and turf restoration. The requirement is split into two unfunded phases, each with its own CLIN, and the government may award one or both phases only if funding becomes available. For Phase 1, the period of performance includes a 90-calendar day non-performance period followed by a 90-calendar day performance period; Phase 2, if awarded, adds a 275-calendar day performance period. A site visit is scheduled for June 3, 2026, at 8:30 AM CST, and all visitors must comply with Vance AFB access requirements. No budget amounts are specified in the description.