REPLACE OLD EXHAUST FANS OF EM#1,S-3109, CP TANGO
Amendment to answer the questions. Please see the attached amendment.
Amendment to answer the questions. Please see the attached amendment.
This is a Request for Proposal to replace the entire cooling tower system at Camp Humphreys, and it is open only to existing General Construction MAIDIQ contractors. The project has an estimated price range between $500,000 and $1,000,000. A site visit is strongly recommended for all contractors intending to propose, and an Excel sheet for it must be submitted by 5 March at 1430 hours. All services will be performed at Camp Humphreys.
This project is to replace the entire cooling tower system at USAG Humphreys, with work to be performed at Camp Humphreys. It is a Request for Proposal issued exclusively to existing General Construction MAIDIQ contractors. The estimated price range for the project is between $500,000 and $1,000,000. A site visit is strongly recommended for all intending bidders.