The scope includes testing of the passive floodwall system manufactured by Floodbreak and constructed in 2019 along Westfield Blvd., demolishing the existing stoplog closure base concrete and replacin...
The scope includes testing of the passive floodwall system manufactured by Floodbreak and constructed in 2019 along Westfield Blvd., demolishing the existing stoplog closure base concrete and replacing with new reinforced concrete with a matching seal plate, and performing CCTV inspections and providing the required documentation on pipes installed in 2018-2019 on the Phase 3B-3 section of the Indy north Flood Risk Management Project.