Mississippi River, Baton Rouge to the Gulf, Saltwater Barrier Sill, Cutterhead Dredge Contract No. 2-2025. Specification No. OM25136
This contract is for the hydraulic dredging and placement of material to construct and potentially maintain a saltwater barrier sill on the Mississippi River between Mile 63.0 and 64.0 Above Head of Passes, near Baton Rouge to the Gulf. The work involves using material from a specified river-bottom borrow area. The estimated construction cost for the project is between $10 million and $25 million. The performance location is the specified stretch of the Mississippi River.