MARKET SURVEY SOURCES SOUGHT NOTICE FOR BARRIER IIB ATS SYSTEMS REPLACEMENT
USACE Chicago District is conducting a market survey for turnkey replacement and modernization of the Barrier IIB Automatic Transfer Switch and Emergency Generator Paralleling Switchgear controls. The work includes engineering, procurement, programming, fabrication, removal, installation, testing, commissioning, and migration from obsolete proprietary controls to open-architecture COTS PLC/HMI and industrial Ethernet systems. Performance is at the Chicago Sanitary and Ship Canal Electric Dispersal Barrier Facility, 790 East Old Romeo Rd., Lockport/Romeoville, IL 60441. Estimated project magnitude is between $250,000 and $500,000, with pre-engineering/procurement/programming/simulation estimated at 90–120 calendar days from Notice to Proceed and on-site installation, cutover, testing, and training up to six consecutive calendar days. The contractor must maintain 24/7 emergency power continuity during cutover, and market survey responses will inform acquisition planning and set-aside determination.