Wolf Creek Turbine Generator Rehab
The U.S. Army Corps of Engineers anticipates a firm fixed-price construction contract to rehabilitate turbine generator units at Wolf Creek Powerhouse in Jamestown, Kentucky. The estimated project magnitude is between $100,000,000 and $250,000,000. The contractor will design, manufacture, and install Francis turbines, rewind generators for Units 1-3 and 5, and refurbish associated equipment for all Units 1-6. The design and manufacturing timeline for the first unit is estimated at 37 months, with unit outages lasting up to 24 months for the first unit and 18 months for subsequent units. Responses to this market research survey are requested by 1:00 PM Central Time on July 9, 2026.