The following specifications and supporting installation of the transmission dyno electrical components are required to bring this equipment to fully mission capable/operational status: Removal and di...
The following specifications and supporting installation of the transmission dyno electrical components are required to bring this equipment to fully mission capable/operational status: Removal and disposal of existing inverter in dyno bay Install MATES #64 supplied inverter package in location of existing ABB inverter. Re-work 3” conduit as necessary to connect new inverter. Furnish and install new line and load-side conductors for inverter. Line-side inverter conductors to be (2) parallel runs of (3) 350 MCM copper. Load-side conductors to be (3) parallel runs of (3) 500 MCM copper. All conduit to be EMT. Commissioning assistance of up to 8 hours to assist PowerTest and MATES #64 dyno representative for start up.