Sources Sought - FY26 Brunswick Inner Harbor Maintenance Dredging Project
This is a market research request for civil works construction involving maintenance dredging in Brunswick Harbor, Georgia. The estimated project magnitude is between $1,000,000 and $5,000,000, with an anticipated performance period of 120 days after notice to proceed. The work involves removing up to 500,000 cubic yards of material from specified areas within the Brunswick Inner Harbor using a hydraulic cutterhead dredge. The dredged material will be placed in the Andrews Island Dredged Material Containment Area, and the work is subject to environmental timing restrictions, including a prohibition on placing material at Andrews Island from mid-April through mid-August. Interested parties are asked to provide capability statements detailing relevant experience, including performing hydraulic dredging to depths of -43 feet MLLW with long pumping distances.