Midwest City Water Tower

Notice ID:W912BV26RA027

This is a pre-solicitation notice for the construction of a 500,000-gallon elevated water tower and associated infrastructure in Midwest City, Oklahoma. The project includes a new high service pump station, piping reconfigurations, and approximately 650 linear feet of new water main. The estimated construction cost is between $10,000,000 and $25,000,000, with a performance location in Oklahoma County, Oklahoma. The contract will be a firm-fixed price, unrestricted procurement using the Lowest Price Technically Acceptable approach. The estimated construction duration is 450 calendar days.

Department/Ind.Agency Subtier Office
DEPT OF DEFENSE DEPT OF THE ARMY W076 ENDIST TULSA
  PSC   Y1NE CONSTRUCTION OF WATER SUPPLY FACILITIES