Concord-Fuel System Repairs
This is a pre-solicitation notice with a draft Scope of Work for facility upgrades involving both F-24 tanks (Tank 1 and Tank 2). Work includes replacing grounding and high-level shut-off valves, extending the tank catwalk platform, installing a check valve on the relief discharge into Tank 2, and completing supply, installation, and testing of an Automatic Tank Gauging (ATG) system. The project also covers installing a truck offload meter, visual fuel flow indicator, eyewash station, filter separator maintenance platform, integrated truck overfill prevention, and ground verification systems for the truck offload/fillstand. Additional tasks include installing protective pipe bollards, replacing the equipment shelter ground system, and providing a ground verification system for offload operations.