Inactive
Total Small Business Set-Aside (FAR 19.5)
Notice ID:W9128F25QA025
Please see attachments for the Combined Synopsis/Solicitation for SP-POL-CMP-INSPECT-FY25-FWY (PO 28) *****Q&A***** (March 12th, 2025) Question 1 Can both tanks can be removed from service back-to-bac...
Please see attachments for the Combined Synopsis/Solicitation for SP-POL-CMP-INSPECT-FY25-FWY (PO 28) *****Q&A***** (March 12th, 2025) Question 1 Can both tanks can be removed from service back-to-back for cleaning, repairs and inspections? Answer 1 The tanks will need to be taken down one at a time. Question 2 What type of IFRs (internal floating roofs) are in the tanks? Answer 2 Per the installation, they are Petrex aluminum honeycomb panel floating roofs with cast rubber wiper seals.