Inactive
Total Small Business Set-Aside (FAR 19.5)
Notice ID:W9128F20Q0066
Amendment 0001 Post and contains the changes identified in the Site Visit meeting minutes. Fort Randall Pestock Joint Packing #8: Entire work complete to replace double expansion joint packing and har...
Amendment 0001 Post and contains the changes identified in the Site Visit meeting minutes. Fort Randall Pestock Joint Packing #8: Entire work complete to replace double expansion joint packing and hardware in penstock #8 including all labor, materials, and equipment. The period of work will begin on February 15, 2021 and must be completed no later than April 2, 2021. Fort Randall Pestock Joint Packing #3: Entire work complete to replace single expansion joint packing and hardware in penstock #3 including all labor, materials, and equipment. The period of work will begin on March 15, 2021 and must be completed no later than April 30, 2021. Refer to Solicitation, Specification and Drawings for more information.