John Day Dam Fish Pump Rehabilitation Project
The John Day Fish Pump Rehabilitation Project at John Day Lock and Dam in Rufus, OR involves removal, refurbishment, and replacement of major components of Fish Pump Unit 1, including shafts, bearings, bearing brackets, and right-angle drive gearboxes. The estimated construction magnitude is between $5,000,000 and $10,000,000, and the opportunity is a total small business set-aside under NAICS 237990 with a $45,000,000 size standard. Amendments added several technical attachments (now downgraded from CUI), removed one attachment, revised specifications, and extended the outage window through June 30, 2028. To access CUI attachments, bidders must verify a minimum CMMC Level 1 self-verification and submit their CMMC Unique Identifier Number and CAGE Code via email. Prospective bidders should also note that the solicitation has been amended to revise inquiry provisions and other requirements.