Pad-Mounted Transformer

Total Small Business Set-Aside (FAR 19.5)
Notice ID:W911S226U3773

This opportunity involves furnishing one specific 750 kVA pad-mounted transformer with detailed technical, mechanical, and electrical requirements, including mandatory physical dimensions and compliance with ANSI, DOE, and NEC standards. The transformer must be delivered fully assembled to Fort Buchanan, Puerto Rico, with an estimated completion time of 40 weeks. The contractor must provide factory routine test reports, certified as-built drawings, and a minimum one-year manufacturer warranty. No budget amount is specified in the description. The location for performance of services is Fort Buchanan, Puerto Rico 00934.

Department/Ind.Agency Subtier Office
DEPT OF DEFENSE DEPT OF THE ARMY W6QM MICC-FT DRUM
  PSC   6120 TRANSFORMERS: DISTRIBUTION AND POWER STATION


Data sourced from SAM.gov. View Official Posting »