The work under MLWR23-1022, Repair Taxiways ABCDEP consists of furnishing all labor, equipment, materials, transportation, and supervision necessary to perform all the work as shown on the drawings an...
The work under MLWR23-1022, Repair Taxiways ABCDEP consists of furnishing all labor, equipment, materials, transportation, and supervision necessary to perform all the work as shown on the drawings and indicated herein. The total duration of the contract should not exceed 360 calendar days. The actual site work period shall be 210 calendar days not to enter November through March. 24 hours operations are allowed upon receipt of NTP (Notice to Proceed). The inside of hold position marking area, taxiway E, and taxiway P (Range from sliding gate for commercial airport to the intersection with taxiway C) must be completed in concurrence with the runway closure period (April through June on 2023).