180th FW Lift Station Repair

Total Small Business Set-Aside (FAR 19.5)
Notice ID:W50S8S26QA009

The contractor must replace one submersible pump and one soft starter at the 180th Fighter Wing main lift station in Swanton, Ohio. All work, including removal, installation, integration, and testing, must comply with the Performance Work Statement. The project requires a new Gorman-Rupp SF Series pump and an Allen-Bradley soft starter, along with as-built drawings and O&M manuals. Work must be completed within 90 calendar days after contract award. No budget amount is specified.

Department/Ind.Agency Subtier Office
DEPT OF DEFENSE DEPT OF THE ARMY W7NU USPFO ACTIVITY OHANG 180
  PSC   Z2ND REPAIR OR ALTERATION OF SEWAGE AND WASTE FACILITIES


Data sourced from SAM.gov. View Official Posting »