COMPUTER,DIGITAL
This is a critical flight/shipboard application item requiring Naval Air Systems Command engineering source approval, with award limited to approved sources; unapproved companies may pursue approval through a Source Approval Request. The contractor must meet ISO 9001 or higher, perform 100% inspection of critical/major characteristics and NDT, maintain part traceability, and conduct First Article Testing for dimensional/form compliance to drawing 3429AS6920 and referenced NAWC Lakehurst drawings. NDT providers must be NADCAP accredited or ISO 17025 accredited. Non-bid timelines include 14 days’ notice before First Article testing, a First Article Test Report within 15 days of testing, Government approval notification within 45 days after inspection, 14 days’ notice before final inspection, and seven-year record retention. Drawings are not available, MIL-STD-2073 packaging applies, and post-award requests must be submitted through the NAVSUP WSS Vendor Portal/Workflow Pro.