Question #1: How will selected demolition be handled if cooling is required after Work commences? Answer #1: Government requires a construction schedule from the Contractor to permit the Government to...
Question #1: How will selected demolition be handled if cooling is required after Work commences? Answer #1: Government requires a construction schedule from the Contractor to permit the Government to schedule and coordinate laboratory down time. See also Question & Answer #2. Question #2: Who provides temporary cooling? Answer #2: Government will provide requisite temporary cooling. Question #3: Will any of the trades need to include off hours work to complete? Answer #3: Power outages may require off work hours. If you cannot participate in this contract opportunity, please email a brief explanation such that we can continuously improve our contracting processes. (End of Questions and Answers) Amendment 0002 revises NAICS Code from 238220 Plumbing, Heating, and Air-Conditioning Contractors to 236220 Commercial and Institutional Building Construction. Updates Sections A through K, minor updates to Sections L and M, and no update to drawings or statement of work. Quote due date extended to 2:00 PM ET Wednesday 11 May 2022. Amendment 0001 provides: 1. Adjust contractual delivery date from 180 days to 320 days after date of contract. 2. Extend quote due date/time to 2:00 PM ET Friday 18 Feb 2022. 3. Provide updated Official Onsite Visitors - Access Control Instructions. See General Information and Attachments J-8 and J-11. 4. Provide Wage Determination RI20220001 dated 2022-01-07. See Attachment J-1. B1404 Shielded Room requires additional cooling, specifically air-cooled split systems with ducted ceiling mounted evaporators with EC motors and remote air-cooled DX condensers with epoxy-coated coils. Evaporators with a condensate pump. Copper tube/aluminum fin for evaporator coil. Condensing units able to operate at low ambient temperature as low as -30°F. Internal smoke detector. Remote temperature sensors and digital wall display. See B1404 Shielded Room Additional Cooling Statement of Work and Drawings FAR 36.204 Disclosure of the magnitude of construction project: Estimated price is between $100,000 and $250,000. Site Visit: 2:00 PM ET Wednesday 20 Oct 2021. Register with NUWC Security and separately with NUWC Contracting Department. See Section A. Questions due: Wednesday 27 Oct 2021 before 2:00 pm ET. Email to Joseph.Scarpa@navy.mil and Kathleen.Hourihan@navy.mil Quotes due: Wednesday 10 Nov 2021 before 2:00 pm ET. Email to Joseph.Scarpa@navy.mil and Kathleen.Hourihan@navy.mil 100% Small Business Set-Aside: NAICS 238220 - Plumbing, Heating, and Air-Conditioning Contractors; Size Standard $16,500,000.00. Technical information required with proposal. See Sections L and M. Complete and submit attached FAR Provision 52.204-24 with proposal. Method of Payment: Government Purchase Card. Ensure your quote includes your expenses for merchant bank processing (your credit card processing fee to your financial institution).