Cisco Firewall Trey Mounts
This requirement seeks fabrication and delivery of 54 custom metal mounting plates to support firewall replacement aboard LCS Freedom Variant ships, with the contractor manufacturing to Government-furnished engineering drawings and specifications. The final engineering drawing is expected to be available in September 2026, with fabrication to begin after receipt and initial ship installation planned for October 2026. Delivery must support the installation schedule: 6 plates by 12 October 2026, 18 plates by 1 November 2026, and 30 plates by 1 December 2026. The plates must be defect-free, suitable for shipboard installation, and packaged to prevent damage during shipment. This effort supports fleet cybersecurity modernization and minimizes installation delays.