Inactive
Notice ID:N50054-20-T-0004
The contractor shall provide technical support IAW the attached SOW to conduct: a. The contractor shall provide labor and material to perform chelate flush in accordance VLS IMS-5982374-1 REV D. Contr...
The contractor shall provide technical support IAW the attached SOW to conduct: a. The contractor shall provide labor and material to perform chelate flush in accordance VLS IMS-5982374-1 REV D. Contractor shall also be responsible for hazmat disposal. b. Contractor shall provide labor and material to remove, overhaul, install, and test 106 deluge valves in accordance with IMS-4810-5497337-3 REV L ACN-3M, MRC 7211/U01 U-A5, MRC 7211/015 72M-1 and approved VLS test procedure AVP-20150526A. 90 valves shall be from VLS system while the remaining 16 valves shall be from ship supply assets. Accomplish valve testing IAW MIP 7211/015 MRC A-5R c. Contractor shall provide labor and material to perform pinhole epoxy impregnation repairs on 16 deluge valves in accordance with VLS IMS 4810-5497361-1.