PUMP
This opportunity is for the repair of a pump under a firm-fixed-price contract for the U.S. Navy. The required Repair Turnaround Time (RTAT) is 182 days, with accelerated delivery encouraged, and performance will be at the contractor's facility with freight handled FOB Origin. Quoted prices may be Estimated, Not-to-Exceed, or Firm-fixed, and the government intends to add an option quantity for increased supply. A price reduction will apply per unit per month if the contractor fails to meet the required RTAT, with the contractor specifying the reduction amount. Government Source Inspection (GSI) is required, and all repair work must meet operational and functional requirements per specified standards.