B334 Repair Kitchen Flooring
The project requires demolishing and replacing the existing quarry tile system in the kitchen and dishwashing area (approximately 4,984 SF of flooring and 800 LF of cove base) with a new resinous flooring system at Building 334, Fort Griffin Avenue, Goodfellow AFB, TX. The work includes repairing walls where needed and must be coordinated during exodus to minimize downtime, with asbestos testing required prior to starting. The period of performance is 164 calendar days after the Notice to Proceed. The contractor must comply with environmental protection requirements, submit SDS sheets for hazardous materials, and report construction and debris metrics and waste diversion. No specific budget amount is provided in the description.