Inactive
Notice ID:FA301619U0191
Replace all existing boiler tubes in boiler #2, clean tube sheets, and install new gaskets. Reassemble boiler #2 and hydro test the unit after repairs are completed in accordance with Statement of Wor...
Replace all existing boiler tubes in boiler #2, clean tube sheets, and install new gaskets. Reassemble boiler #2 and hydro test the unit after repairs are completed in accordance with Statement of Work, Attachment 1 and Attachment 2. Site Visit. A site visit will be conducted on 10 July 2019 (Wednesday) @ 9:30 AM CST at JBSA Lackland TX Building 10426. To attend the site visit, please respond to Jack Caniglia at the jack.caniglia.3@us.af.mil with your intent to attend. If you need a base pass to enter JBSA Lackland please email Jack Caniglia the following information not later than 09 July 2019, Tuesday. at 10:00 AM CST.