FY26 Boiler Inspections
The contractor will inspect and repair mission-critical equipment at Hanscom AFB, Massachusetts, including four boiler units, one Heat Recovery Steam Generator (HRSG), and associated systems. The objective is to identify and correct deficiencies to prevent system failures. A site visit is scheduled for August 25, 2026, from 9:00–11:00 AM, with arrival by 8:15 AM at the Hanscom AFB Visitor Center. Questions are due by 2:00 PM EST on August 26, 2026, with answers provided by August 28, 2026. Additional requirements are detailed in the Performance Work Statement.