Nez Perce-Clearwater NF - Seed Orchard Disconnect and Electrical Life Safety Rehab

Total Small Business Set-Aside (FAR 19.5)
Notice ID:1240LU26Q0068

This opportunity involves relocating overhead power to underground, installing a new electrical disconnect, and replacing pump controls at the Salmon River Seed Orchard Pump Station to correct hazardous electrical deficiencies. The project is a total small business set-aside, with a size standard of $45 million under NAICS code 237130. Performance and payment bonds are required at 100% of the contract price if the value exceeds $150,000, due 10 days after award. A site visit is scheduled for July 7, 2026, and questions are due by July 13, 2026. The location for performance is the Salmon River Seed Orchard Pump Station.